January 2012 | Issue 4
Welcome to the Harlequin Newsletter for January |
In this issue:
The Hideaway update
Las Canas Resort update
Two Rivers Resort update
The Merricks Resort update
H Barbados update |
 |
 |
The Hideaway
Full project design is 90% complete. Harlequin Developments met with Escarfullery & Asociados on 19th January to discuss detailed design works, finishings and bill of quantities. All 3D model analysis and spatial studies have been completed; the Harlequin Hotels & Resorts team will now work with Harlequin Developments and Escarfullery to refine the operational components of the design. This is in order to ensure efficient running of the hotel and to maximise the guest experience of the facilities. Detailed design work for spa space will commence with ESPA
early in the New Year.
|

Computer Generated Image (CGI) of The Hideaway Interior

The Hideaway Master Plan
|
 |
 |
Las Canas
A Wetland delimitation survey is being carried out to satisfy EIA requirements. River defence studies have been completed. Harlequin Developments and Harlequin Hotels & Resorts met with Escarfullery & Asociados on 18th January 2012 to review final conceptual design for Phase 1 and establish a working schedule for EIA studies.
|

Las Canas Delimination Survey Image
|
 |
 |
Two Rivers
Environmental studies for the EIA had been completed and introduced for permission for planning based on the new master plan design. The EIA studies were conducted again because additional land was purchased to expand facilities in line with brand growth. The new plan will enable Harlequin to deliver an even more attractive resort. Harlequin Developments met with Escarfullery & Asociados on 19th January to discuss detailed design works.
|

Two Rivers Master Plan
|
 |
 |
The Merricks Resort
The master plan is being developed in greater detail to assist the resolution of the 19 points of the conditions of planning in accordance with Town and Country planning requirements.
Additional reports needed by Town and Country planning are also
in various stages of development, with some now complete. These
are on track for the March 2012 submission, as scheduled by Harlequin Developments.
Work Carried Out
 |
Guard hut substructure completed |
 |
Reinforcement to Guard hut complete |
 |
Guard hut slab cast (3750 psi concrete) |
 |
Wet service trench 90% excavated |
 |
Installation of sewage pipe 80% complete |
 |
Installation of rain water pipe 80% complete |
 |
Installation of potable and rain water supply 80% complete |
 |
Backfill to wet service trench 75% complete |
 |
Electrical inspection to Villa D and F pool passed |
 |
Villa D Pool slab cast (3750 psi concrete with water proofing) |
 |
Villa F Pool slab cast (3750 psi concrete with water proofing) |
 |
Excavation to electrical service trench 80% completed |
 |
Manufacture window and door shuttering for Villa D and F superstructure 75% complete |
|

The Merricks Resort CGI

The Merricks Resort Pool Slab

The Merricks Resort Master Plan
|
Procurement
 |
Windows and doors ready for export, awaiting inspection in Miami |
 |
Gazebo being manufactured in Panama |
 |
"Enviroshake" tiles ready for dispatch from Canada |
 |
Sanitary ware (toilets, sinks, baths, etc.) have
been ordered from China for the show homes |
Challenges
 |
Due to late delivery of ICF on site, installation did not commence until January 5th |
 |
Electrical installation to villa D caused 5 days delay on the super structure, but this was due to a learning process with a new method of construction.
Lessons have been learned and procedures implemented on Villa F to overcome these issues
|
 |
Awaiting water to be connected due to Barbados Water Authority awaiting water meters |
 |
Late delivery of villa pool equipment specification |
|
Tender Processes
 |
Roofing package tender was awarded first week of January |
 |
Mechanical contract out to tender |
 |
Gazebo installation out to tender |
 |
Civil works being carried out |
Programme
 |
ICF to Villa D is behind programme due to late delivery to site |
 |
ICF to Villa F, same as above |
 |
A significant delay was caused by issues with
delivery of ICF; however, the programme is currently
being reworked to identify where this could be
mitigated. One example is that ICF could be installed to all buildings
at once |
 |
The new programme was issued 18th January |
|
 |
 |
H Barbados
Work Carried Out
 |
Block C scaffolding removal is 100% complete, which allows for the excavation of the piling mat |
 |
Block A demolition is 90% complete. Only the floor slab, foundations and 2 flights of the stair well remain. Completion of the demolition has been delayed by the existing live service connection to the switch gear in the bottom of the stair well. Barbados Light & Power are responsible for the current transformer on site and have not yet agreed a date when they can shut down. Upon disconnection, the final completion duration is expected to be 1 day |
Design
 |
Received mock-up room architectural drawings on site (20/12/11) |
 |
Received mock-up room interior designer drawings and specs on site (21/12/11) |
 |
Awaiting construction drawings |
 |
Awaiting MEP (mechanical, electrical and plumming) drawings |
 |
Civil Engineers, Adams Consulting International (ACI) are awaiting details of geotech (studies of the strata and earth make-up beneath the buildings) reports to finalise foundation designs |
 |
Location of mock-up room is confirmed Ocean G-1 / Beach 1-2 |
 |
ACI requested to provide information for all structural elements to the mock-up rooms 009-HBH-RFI. |
|
Procurement
 |
Take offs are being completed for the mock up rooms |
 |
Harlequin Developments has received samples from the interior design team, NODA, and has begun the procurement of materials in order to build two show rooms to refine design and conduct checks |
Tendering
 |
Awaiting design for the foundations to block C and block A, but preliminary discussions have taken place regarding piling solutions with companies |
 |
Sign Station have been engaged for the installation
of the signage to the hoarding |
 |
Complete mock-up room packages have been sent to two sub-contractors for pricing, both as labour only and material supply. Three sub-contractors have been selected to price the individual elements of each mock-up room |
Programme
 |
Demolition of block C is complete 3 weeks ahead of programme |
 |
Despite delays, Block A demolition is ahead of programme |
Please click here to watch a video of the Block C demolition.
|
|
|
|
You can also call Harlequin Property on: 0845 8884422 or +44
(0)1268 242460
You have received this email because you are subscribed to the Harlequin
Hotels & Resorts mailing list. You can unsubscribe from the mailing list by clicking
Unsubscribe.
It can take up to 3 working days to be unsubscribed from our system. Please - Do not reply to this
email address as this mailbox is not monitored.
The information contained in this email and any attachments is
confidential. It is intended solely for the named addressee(s).
It may be privileged or exempt from disclosure under applicable
law. If you are not the addressee or have received this email in
error, please notify the sender immediately, delete it from your
system and do not copy, disclose or otherwise act upon any part
of this email or its attachments.
Internet communications are not guaranteed to be secure or virus
free and Harlequin Hotels & Resorts does not accept responsibility for
any loss arising from unauthorized access to, or interference
with, any Internet communications by any third party, or from
the transmission of any viruses. All information or opinions
expressed in this message and/or any attachments are those of
the author and are not necessarily those of Harlequin Hotels &
Resorts.
Harlequin Hotels & Resorts Limited. Company Registration no: 195924.
Registered Office Address: PO Box 32322, 4th Floor Century Yard,
Cricket Square, Elgin Avenue, Grand Cayman KY101209 Cayman
Islands.
Tel: 0845 8884422 or +44 1268 242460 Fax: 0845 8884433 Web:
http://www.harlequinhotelsandresorts.com
|
|
|
|